Sewer Infrastructure Rehabilitation Complete

Belmont

Summary

The 2025 Sewer Rehab Project — about 6,049 feet of sewer replacement plus storm drain work — was formally accepted as complete at a final cost of $1,815,746.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 8, 2026.

Impact analysis

💰Financial impact

Final cost $1,815,746, within the approved contingency, with retention released 35 days after the Notice of Completion is filed.

✅Who benefits

All Belmont residents who rely on the sanitary sewer system.

⚠️Who could be affected

No groups negatively affected